Asphalt road work to begin in Butler County

road-construction-sign-2

Butler County Engineer John Riherd tells Radio on the Go News that their asphalt resurfacing project will be kicking off in earnest this week.

A one mile stretch of Newell Avenue north of Highway 3 and 9 miles of county road C-13 from Packard Avenue east to Bremer County will be under construction. Multiple contractors will be on site over the next 8 weeks or so.

Milling and cold in-place recycling begins this week, and will last about 10 days. Drying time for recycled pavement will last about 2 weeks.

Asphalt paving is scheduled for mid-June, lasting 2-3 weeks.